Today in this post you will find information about Engineering Estimating. The types of estimates and their purpose of estimation. I hope this article is beneficial to you in estimating information. Read this post till the end of the page. so let’s get started:
You are an engineer, estimator, and contractor. This is the most important part of the engineering sector. Without an estimate, the construction cannot be possible in the different categories. Like cost, period, required engineering materials, required labor, etc. This is the pre-planning of Construction Technology. Engineer, contractor, and estimator can perform estimates of any construction.
This is performed before the construction. The estimate gives the value of the cost of construction, the number of members required for the construction, the type of engineering materials, and the time for completion of the project.
What is Estimation?
It appears that the qualifier is a record of the materials, items of work, cost of the project, number of labor, period, and expenditure likely to be incurred in the construction of a building, highway, road, dam, boundary wall, irrigation, etc. The estimate gives the probable cost of work. It is determined by theoretical calculations based on plans, drawings, and current rates.
What is the purpose of estimation?
To know the probable cost of the project or work.
Know the approximate quantity of the material and labor required for the project.
Have an idea about the time of completion of the project.
To help control the expenditure during execution.
Support to check the work done by contractors.
Inviting tenders and arranging contracts.
For technical sanction of the project.
To help in help fixing standard rent, the sale price of flats, and the valuation of properties.
Collect necessary tools and plants as per the schedule of the project in the required numbers.
Create a schedule of work.
To justify the cost-benefit ratio.
What are the types of estimation?
The following are the various estimating types. Which list below with details:
- Preliminary estimate approximate estimate or rough estimate.Â
- Plinth area estimate.
- Cube rate estimate or cubical content estimate.
- Approximate quantity method estimate.
- Detail estimate or item rate estimates.
- Revised estimate.
- Supplementary estimate.
- Supplementary and revised estimate.
- Complete estimate.
- Annual maintenance or repair estimate.
Preliminary estimate
Building:-
Approx. Quantity method.
- Per km basis.
- Per hector basis (area of land commanded)
- Bridge and culvert:- Per running meter of span depending upon the type of structure, type, and depth of foundation.
- Sewage and water supply project:
- Per head of population served.
- Per hectare basis (area covered)
Plinth area estimate
In this method of estimate, the plinth area of the building is calculated for the plinth area estimate.Â
The external dimensions of the building floor level were taken to find out the plinth area.Â
Courtyard and other open should not be included.
For multi-story buildings plinth area for each story is determined separately.Â
The approximate total plinth area may be calculated by adding 30 % to 40 % of the already calculated building having the same specification as the previously constructed building having the same specification and locality.
The cost of the new building is out in this method of estimate by multiplying the plinth area by the respective rate item of the project. Rate
Rate= cost of construction/plinth area.
The Cost of the new building = plinth area * Rate of items of the project.
Cube rate estimate:
A cube rate estimate is also an approximate estimate.
The cubical content of the building is determined by multiplying the length breadth and height of the building.Â
Floor level to top level of floor height should be taken to find out the cube.
For a multi-story building, height takes from the floor level of one story to the top of the next higher floor.
The cube rate estimate is more accurate as compared to the plinth area estimate.
Approximate quantity estimate method
The total length of the walls is found out.
To find a running meter rate of the foundation, approx. Quantities of different items are calculated per the running meter of the project.Â
Similarly for superstructure approx. Quantities of brickwork on the wall, top roof, flooring, etc. Is calculated per running meter.
Supplementary estimate
It is the type of detailed estimate when additional work is to be done in the project and then the supplementary estimate is done in the original estimate document.Â
It is required when further development of the project requirements during the progress of work or project.Â
In this type of estimate, the amount of the original estimate and the final estimate a categorized into two parts. Like abstract amount shouldbe includede in the original estimate and the supplementary amount included in the final estimate.
The original estimate was called an obstruct amount.
Obstruct amount + supplementary amount = final amount of project.
The supplementary and revised estimate
When work is partially abandoned and the estimated cost of the remaining work is less than 95% of the original sanctioned estimate.
It is done when there are material deviations or fluctuations and changes in the design properties.
If at any time before or during the execution of the work, it is found that the original estimate is excessive then the divisional officer may sanction a revised estimate of reducing the amount.
Detailed estimate
It is an accurate type of estimate. Which is prepared by working out quantities of every item of work. In this estimate, the individual items are included in the detailed estimate. This includes the detailed particulars items for the quantities, rates, and costs of all the items included for satisfactory completion of the project or work.
In the detailed estimate, the quantities of all items of the project are calculated from the respective dimensions of the design drawing on a measurement sheet. After completing the quantities of all items then simply multiply by the respective rate of an item of work to find the cost of the item. This is the best and most accurate estimate that can prepare a detailed estimate.Â
A detailed estimate is complete by the following topic:
- Report
- Specification
- Detailed drawings showing plan, section, elevation, side view, and key and index plan
- Design data and calculations
- Basic respective rates adopted in the estimate
- It is prepared in two stages:
- Details of measurement and calculation of quantities.
- Abstract of estimated cost 3% to 5% of the estimated cost added to cover miscellaneous expenditure.Â
- A detailed estimate is prepared to work.
- A detailed estimate is prepared for sanction, for arranging the contract, and for the execution of the project.Â
Complete estimate
Cost of land
- Cost of legal expenses required between an owner and the contractor.
- Cost of main contract or material, labor, and Suspension.
- Contingency 5% of the work or extra work.
Engineering fee
- Cost of preparation of plan, design, and estimate.
- Cost of supervision work.
Annual maintenance or repair estimate
Contingencies
Administrative approval
After visiting this article, you get the information about the estimation. I hope you understand the purpose and type of estimate in this article. If this article is helpful for you to have any doubt please comment me.
Â
Thank you so much, Visit again.